Submissions from 2026
Draft Final 2023 Unreclaimed Sites Sampling: UR-42 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Draft Final 2023 Unreclaimed Sites Sampling: UR-43 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Draft Final 2024 Reclamation Improvement Sampling: BRES No. 78 – Original Mine Yard Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Draft Final 2024 Unreclaimed Sites Sampling: UR-21 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Draft Final 2024 Unreclaimed Sites Sampling: UR-46 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Draft Final 2025 BPSOU Subdrain Data Summary Report (DSR), Pioneer Technical Services, Inc.
Draft Final Annual Operations and Maintenance (O&M) Report: Butte Treatment Lagoon (BTL) System – 2025, Pioneer Technical Services, Inc.
Draft Final Annual Operations and Maintenance (O&M) Report: Butte Treatment Lagoon (BTL) System – 2025, Pioneer Technical Services, Inc.
Draft Final BPSOU Unreclaimed Sites: UR-46 Remedial Action Work Plan (RAWP), Pioneer Technical Services, Inc.
Draft Final Butte Mine Waste Repository Operation and Maintenance (O&M) Plan, Pioneer Technical Services, Inc.
Draft Final Butte Priority Soils Operable Unit (BPSOU) Insufficiently Reclaimed Sites BRES No. 30 – Atlantic 1 Remedial Action Work Plan (RAWP), Pioneer Technical Services, Inc.
Draft Final Butte Priority Soils Operable Unit (BPSOU) Insufficiently Reclaimed Sites Sister Dump (BRES No. 38) Remedial Action Work Plan (RAWP), Pioneer Technical Services, Inc.
Draft Final Butte Priority Soils Operable Unit Insufficiently Reclaimed Sites Temporary Best Management Practices Work Plan: BRES No. 16 – Curry and BRES No. 50 – Zelia, Pioneer Technical Services, Inc.
Draft Final Butte Priority Soils Operable Unit Unreclaimed Sites: UR-03 Construction Completion Report, Pioneer Technical Services, Inc.
Draft Final Butte Priority Soils Operable Unit Unreclaimed Sites: UR-03 Construction Completion Report, Pioneer Technical Services, Inc.
Draft Final Butte Priority Soils Operable Unit Unreclaimed Sites: UR-35 Construction Completion Report (CCR), Pioneer Technical Services, Inc.
Draft Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System – First Quarter 2026, Pioneer Technical Services, Inc.
Draft Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System – Fourth Quarter 2025, Pioneer Technical Services, Inc.
Draft Final Silver Bow Creek Conservation Area Materials Management Plan Revision 1, Pioneer Technical Services, Inc.
Draft Final Silver Bow Creek Conservation Area (SBCCA) Butte Reduction Works (BRW) Air Monitoring for Interim Demolition Activities – Phase II Data Summary Report (DSR), Pioneer Technical Services, Inc.
Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 16 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 30 – Atlantic-1 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 32 – Corra 2 Dump Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 37 – Josephine Shaft Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 38 – Sister Dump Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 96 – Washoe Dump Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-06 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-07 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-12 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-13 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-20 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-22 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-28 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2022 Unreclaimed Sites Sampling: UR-28 Site Evaluation Summary ReportFinal 2022 Unreclaimed Sites Sampling: UR-28 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final 2023 Unreclaimed Sites Sampling: UR-42 Site Evaluation Summary Report, Pioneer Technical Services, Inc.
Final Annual Operations and Maintenance (O&M) Report: Butte Treatment Lagoon (BTL) System – 2023, Pioneer Technical Services, Inc.
Final Basinwide Quality Management Plan (QMP) – 2026-2030, Revision 0, Pioneer Technical Services, Inc.
Final BPSOU Unreclaimed Sites: UR-46 Remedial Action Work Plan (RAWP), Pioneer Technical Services, Inc.
Final Butte Priority Soils Operable Unit (BPSOU) Unreclaimed Sites: UR-08 (Anderson Shaft) Remedial Action Work Plan (RAWP), Pioneer Technical Services, Inc.
Final Butte Priority Soils Operable Unit (BPSOU) Unreclaimed (UR) Sites New and Mahoney (UR-23) Construction Completion Report (CCR), Pioneer Technical Services, Inc.
Final Insufficiently Reclaimed Sites Quality Assurance Project Plan (QAPP), Pioneer Technical Services, Inc.
Final Insufficiently Reclaimed Sites Quality Assurance Project Plan (QAPP), Pioneer Technical Services, Inc.
Final Quarterly Operations and Maintenance Report Butte Treatment Lagoon System – First Quarter 2025, Pioneer Technical Services, Inc.
Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System – Fourth Quarter 2025, Pioneer Technical Services, Inc.
Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System – Third Quarter 2025, Pioneer Technical Services, Inc.
Final Revised Silver Bow Creek Conservation Area (SBCCA) Construction Quality Assurance Plan (CQAP), Pioneer Technical Services, Inc.
Final Silver Bow Creek Conservation Area Materials Management Plan, Pioneer Technical Services, Inc.
Final Silver Bow Creek Conservation Area (SBCCA) Construction Quality Assurance Plan (CQAP), Pioneer Technical Services, Inc.
Final Unreclaimed Sites Quality Assurance Project Plan (QAPP), Pioneer Technical Services, Inc.
Final Unreclaimed Sites Quality Assurance Project Plan (QAPP), Pioneer Technical Services, Inc.
Revised Draft Final Annual Operations and Maintenance (O&M) Report: Butte Treatment Lagoon (BTL) System – 2025, Pioneer Technical Services, Inc.
Revised Draft Final Butte Mine Waste Repository Operation and Maintenance (O&M) Plan, Pioneer Technical Services, Inc.
Revised Draft Final Butte Priority Soils Operable Unit (BPSOU) Insufficiently Reclaimed Sites Josephine Shaft (BRES No. 37) Remedial Action Work Plan (RAWP), Pioneer Technical Services, Inc.
Revised Draft Final Butte Priority Soils Operable Unit (BPSOU) Unreclaimed (UR) Sites New and Mahoney (UR-23) Construction Completion Report (CCR), Pioneer Technical Services, Inc.
Revised Draft Final Butte Priority Soils Operable Unit (BPSOU) Unreclaimed (UR) Sites New and Mahoney (UR-23) Construction Completion Report (CCR), Pioneer Technical Services, Inc.
Revised Draft Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System – First Quarter 2026, Pioneer Technical Services, Inc.
Revised Draft Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System – Second Quarter 2025, Pioneer Technical Services, Inc.
Butte Priority Soils Operable Unit Butte Reduction Works Smelter Area Intermediate 60% Remedial Design Submittal, Pioneer Technical Services, Inc. and Atlantic Richfield Company
Third Butte RMAP Biomonitoring (Phase 3) Report, Ramboll and Atlantic Richfield Company
Re: Approval Letter for the Uncontrolled Surface Flow Areas Drainage C 95% Design Remedial Action Work Plan, Molly Roby