Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Final 2023 Reclamation Improvement Sites Sampling: BRES No. 31 – Waste Dump #5 Site Evaluation Summary Report, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Final Unreclaimed Sites Field Sampling Plan (FSP) Package #7: UR-01, UR-12, UR-03, UR-04, UR-15, and UR-17 Amendment (dated April 28, 2026), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Draft Final 2022 Unreclaimed Sites Sampling: UR-06 Site Evaluation Summary Report (dated December 10, 2025), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Draft Final 2022 Unreclaimed Sites Sampling: UR-12 Site Evaluation Summary Report (dated December 9, 2025), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Draft Final 2022 Unreclaimed Sites Sampling: UR-22 Site Evaluation Summary Report (dated December 10, 2025), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Draft Final Insufficiently Reclaimed Sites Joesphine Shaft (BRES No. 37) – Remedial Action Work Plan (RAWP) (dated March 24, 2026), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Draft Final Unreclaimed Sites: New and Mahoney (UR-23) Construction Completion Report (CCR), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Draft Final Unreclaimed Sites: UR-07 Site Evaluation Summary Report (SESR), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Unreclaimed Sites: UR-03 Construction Completion Report (CCR), Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit - Draft Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 96 – Washoe Dump Site Evaluation Summary Report, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final 2023 Insufficiently Reclaimed Sites Sampling: BRES No. 93 – Soudan Dump Site Evaluation Summary Report, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Insufficiently Reclaimed Sites Field Sampling and Investigation Plan: BRES No. 11 – Magna Charta Lessee Dumps, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Insufficiently Reclaimed Sites Field Sampling and Investigation Plan: BRES No. 1503 – Hornet Addition, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Reclamation Improvement Field Sampling and Investigation Plan: BRES No. 105 – Lizzie Shaft, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Reclamation Improvement Field Sampling and Investigation Plan: BRES No. 129 – Heaney Dump, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Reclamation Improvement Field Sampling and Investigation Plan: BRES No. 135 – Washoe Sampling Works, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Reclamation Improvement Field Sampling and Investigation Plan: BRES No. 46 – Missoula Mine, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit Draft Final Reclamation Improvement Field Sampling and Investigation Plan: BRES No. 75 – National Dump, Molly Roby
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit, Draft Final Unreclaimed Sites: UR-31 Site Evaluation Summary Report, Molly Roby
PDF
Re: Approval letter for the Draft Final 2026 Butte Priority Soils Operable Unit (BPSOU) McDermott Basin Creek Water Treatment Plant Subsurface Fill Borrow Submittal #1, Molly Roby
PDF
Re: Approval letter for the Draft Final 2026 Butte Priority Soils Operable Unit (BPSOU) Type B Borrow Material Submittal #3 (dated May 6, 2026), Molly Roby
PDF
Re: Approval letter for the Draft Final Butte Priority Soils Operable Unit (BPSOU) Unreclaimed Sites: UR-35 Construction Completion Report (CCR), Molly Roby
PDF
Re: Approval letter for the Draft Final Butte Priority Soils Operable Unit Insufficiently Reclaimed Sites Temporary Best Management Practices Work Plan: BRES No. 16 – Curry and BRES No. 50 – Zelia, Molly Roby
PDF
Re: Approval letter for the Draft Final Butte Priority Soils Operable Unit Unreclaimed Sites Field Sampling and Investigation Plan: UR 51 – Area near BRES No.50 –Zelia and Mountain Con Mine, Molly Roby
PDF
Re: Approval Letter for the Uncontrolled Surface Flow Areas Drainage C 95% Design Remedial Action Work Plan, Molly Roby
PDF
Re: Comment letter for the Butte Priority Soils Operable Unit (BPSOU) 2025 Butte Reclamation Evaluation System (BRES) Field Evaluation Summary Report and Technical Recommendations Proposal, Molly Roby
PDF
Re: Comment letter for the Butte Priority Soils Operable Unit (BPSOU) 2025 Butte Reclamation Evaluation System (BRES) Site Specific Corrective Action Plans for Quadrant 2, Molly Roby
PDF
Re: Comment letter for the Butte Priority Soils Operable Unit (BPSOU) 2026 Revised Draft Final Backfill and Cover Soil Quality Assurance Project Plan (QAPP) (dated January 5, 2026), Molly Roby
PDF
Re: Comment letter for the Draft Final Butte Priority Soils Operable Unit (BPSOU) Insufficiently Reclaimed Sites BRES No. 30 – Atlantic 1 Remedial Action Work Plan (RAWP) (dated March 24, 2026), Molly Roby
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit (BPSOU) 2026 Revised Draft Final Backfill and Cover Soil Quality Assurance Project Plan (QAPP) (dated May 13, 2026), Molly Roby
PDF
Re: Conditional Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Draft Final Potential Logan, Montana, Borrow Source Site Environmental Assessment Checklist, Molly Roby
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit (BPSOU) Draft Final Unreclaimed Sites: UR-46 Remedial Action Work Plan (RAWP), Molly Roby
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit (BPSOU) Draft Final Unreclaimed Sites: UR-46 Site Evaluation Summary Report (SESR), Molly Roby
PDF
Re: Conditional Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Revised Butte Hill Revegetation Specifications (dated August 15, 2025), Molly Roby
PDF
Re: Conditional Approval letter for the Butte Priority Soils Operable Unit Draft Final 2022 Insufficiently Reclaimed Sites Sampling: BRES No. 50 – Zelia Site Evaluation Summary Report, Molly Roby
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit Insufficiently Reclaimed Sites Quality Assurance Project Plan, Molly Roby
PDF
Re: Conditional Approval letter for the Draft Final 2024 Unreclaimed Sites Sampling: UR-21 Site Evaluation Summary Report, Molly Roby
PDF
Re: Conditional Approval letter for the Draft Final Butte Priority Soils Operable Unit (BPSOU) Insufficiently Reclaimed Sites Sister Dump (BRES No. 38) Remedial Action Work Plan (RAWP), Molly Roby
PDF
Re: Conditional approval letter with comments for the Draft Final 2026 Residential Metals Abatement Program (RMAP) Anselmo Mine Yard Development Plan (dated February 25, 2026), Molly Roby
PDF
RFC - REQUEST FOR INFORMATION - Waste Rock Dump Stormwater Runoff Collection System Substitution, Molly Roby
PDF
Re: Approval Letter for Draft Final Silver Bow Creek Conservation Area (SBCCA) Butte Reduction Works (BRW) Air Monitoring for Interim Demolition Activities – Phase II Data Summary Report (DSR) (dated June 26, 2026), Emma Rott
PDF
Re: Approval letter for the 2022 Butte Priority Soils Operable Unit (BPSOU) Stormwater Evaluation and Maintenance Report (dated April 8, 2026), Emma Rott
PDF
Re: Approval letter for the 2023 Butte Priority Soils Operable Unit (BPSOU) Stormwater Evaluation and Maintenance Report (dated April 8, 2026), Emma Rott
PDF
Re: Approval letter for the 2024 Butte Priority Soils Operable Unit (BPSOU) Stormwater Evaluation and Maintenance Report (dated April 8, 2026), Emma Rott
PDF
Re: Approval Letter for the Butte Priority Soils Operable Unit (BPSOU) Clark Tailings Consolidated Waste Management Area (CTCWMA) Site Investigation Quality Assurance Project Plan (QAPP) (dated August 14, 2026), Emma Rott
PDF
Re: Approval Letter for the Butte Priority Soils Operable Unit (BPSOU) Clark Tailings Consolidated Waste Management Area (CTCWMA) Site Investigation Quality Assurance Project Plan (QAPP) Revision 0 (2026) Request for Change (RFC)-2026-001 (dated September 8, 2026), Emma Rott
PDF
Re: Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Draft Final Quarterly Operation and Maintenance Report: Butte Treatment Lagoons (BTL) System– Fourth Quarter 2025 (dated March 30, 2026), Emma Rott
PDF
Re: Approval Letter for the Butte Priority Soils Operable Unit (BPSOU) Final 2026 Interim Site- Wide Surface Water Monitoring Quality Assurance Project Plan (QAPP) (dated August 28, 2026), Emma Rott
PDF
Re: Approval letter for the Butte Priority Soils Operably Unit (BPSOU) Revised Draft Final Quarterly Operations and Maintenance Report: Butte Treatment Lagoon System (BTL) Second Quarter 2025 (dated April 10, 2026), Emma Rott
PDF
Re: Approval letter for the Diggings East 100% Remedial Design Package Submittal (dated July 23, 2026), the 100% SBCCA Programmatic Technical Specifications Submittal (Technical Specifications) (dated May 29, 2026), the Final Revised Silver Bow Creek Conservation Area (SBCCA) Construction Quality Assurance Plan (CQAP) (dated July 29, 2026), the Final SBCCA Construction Monitoring Quality Assurance Project Plan (QAPP) (dated July 29, 2026), and the Final SBCCA Materials Management Plan (MMP) (dated July 29, 2026), Emma Rott
PDF
Re: Approval Letter for the Final 2026 Interim Site-Wide Groundwater Monitoring Quality Assurance Project Plan (dated August 28, 2026), Emma Rott
PDF
Re: Approval letter for the Final Repository Siting Study (RSS) Detailed Evaluation and Recommendations Report (dated February 11, 2026), Emma Rott
PDF
Re: Approval Letter for the Quarterly Operations and Maintenance Report Grove Gulch Sedimentation Bay for First Quarter 2026 Silver Bow Creek/Bute Area NPL Site – Butte Priority Soils Operable Unit Consent Decree-Civil Action No. CV 89-039-BU-SHE (Dated May 15, 2026)., Emma Rott
PDF
Re: Approval Letter for the Quarterly Operations and Maintenance Report Grove Gulch Sedimentation Bay for Fourth Quarter 2025 Silver Bow Creek/Bute Area NPL Site – Butte Priority Soils Operable Unit Consent Decree-Civil Action No. CV 89-039-BU-SHE (Dated May 15, 2026)., Emma Rott
PDF
Re: Approval letter for the Revised Draft Final Butte Priority Soils Operable Unit (BPSOU) Butte Treatment Lagoons (BTL) Quarterly Operation and Maintenance Report: Butte Treatment Lagoon System – First Quarter 2026 (dated September 15, 2026), Emma Rott
PDF
Re: Comment Letter for BPSOU Blacktail Creek Riparian Actions Uniform Federal Policy Quality Assurance Project Plan Addendum (dated April 24, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit (BPSOU) 2025 Surface Water Compliance Evaluation Technical Memorandum (dated June 29, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit (BPSOU) Butte Reduction Works Smelter Area Intermediate 60% Remedial Design Submittal (dated May 19, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit (BPSOU) Draft 2025 Groundwater Monitoring Data Summary Report January – December 2025 (dated May 29, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit (BPSOU) Draft 2025 Site-Wide Surface Water Monitoring Data Summary Report (dated May 29, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit (BPSOU) Draft Diggings East Dewatering Treatability Study Pre-Design Investigation Work Plan (PDIWP) (dated August 24, 2026) and the 2026 Draft Diggings East Dewatering Treatability Study Quality Assurance Project Plan (QAPP) (dated August 24, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit (BPSOU), Draft Intermediate (60%) Remedial Design Report, Blacktail Creek Riparian Actions (dated March 13, 2026), Emma Rott
PDF
Re: Comment Letter for Butte Priority Soils Operable Unit Draft Leak Detection Monitoring Plan (dated February 2026), Emma Rott
PDF
Re: Comment Letter for Draft Clark Tailings Consolidated Waste Management Area (CTCWMA) 2024 Data Summary Report (dated October 15, 2025), Emma Rott
PDF
Re: Comment Letter for Draft Final 2026 Interim Site-Wide Groundwater Monitoring Quality Assurance Project Plan (dated April 17, 2026), Emma Rott
PDF
Re: Comment Letter for Old Butte Silver Bow Landfill/Clark Tailings Consolidated Waste Management Area (CTCWMA) Remedy Effectiveness Evaluation Phase I (Conceptual Site Model) (dated February 27, 2026), Emma Rott
PDF
Re: Comment letter for the 2020 through 2024 Surface Water Compliance Evaluation Technical Memorandums Silver Bow Creek Area NPL Site, Butte Priority Soils Operable Unit (BPSOU) Consent Decree-Civil Action No. CV89-039-BU-SHE (dated February 3, 2026), Emma Rott
PDF
Re: Comment letter for the Butte Priority Soils Operable Unit (BPSOU) Draft 2022 Stormwater Evaluation and Maintenance Report (dated February 27, 2026), Emma Rott
PDF
Re: Comment letter for the Butte Priority Soils Operable Unit (BPSOU) Draft 2023 Stormwater Evaluation and Maintenance Report (dated February 27, 2026), Emma Rott
PDF
Re: Comment letter for the Butte Priority Soils Operable Unit (BPSOU) Draft 2024 Stormwater Evaluation and Maintenance Report (dated February 27, 2026), Emma Rott
PDF
Re: Comment letter for the Draft Final Butte Mine Waste Repository Operations and Maintenance (O&M) Plan (dated May 8, 2026), Emma Rott
PDF
Re: Comment letter for the Draft Final Butte Priority Soils Operable Unit (BPSOU) Butte Treatment Lagoons (BTL) Groundwater Treatment System Quarterly Operation and Maintenance Report – Quarter 1 2026 (dated June 26, 2026), Emma Rott
PDF
Re: Comment letter for the Revised Draft Final Butte Priority Soils Operable Unit (BPSOU) Butte Treatment Lagoon (BTL) System Annual Report – 2025 (dated May 11, 2026), Emma Rott
PDF
Re: Comment Letter for the Silver Bow Creek/Butte Area NPL Site Butte Priority Soils Operable Unit, 60% Remedial Design Documents for the Blacktail Creek Area Groundwater Hydraulic Control System (dated March 2, 2026), Emma Rott
PDF
Re: Comment Letter for the Silver Bow Creek/Butte Area NPL Site Butte Priority Soils Operable Unit, Remedial Design Documents for the Blacktail Creek Area Groundwater Hydraulic Control System (dated July 31, 2026), Emma Rott
PDF
Re: Conditional approval Letter for Butte Priority Soils Operable Unit (BPSOU) Butte Treatment Lagoons (BTL) Hydraulic Capacity Improvements Interim Operations and Water Management Plan (dated September 18, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Butte Priority Soils Operable Unit (BPSOU) Final Diggings East Dewatering Treatability Study Pre-Design Investigation Work Plan (PDIWP) (dated September 8, 2026) and the 2026 Final Diggings East Dewatering Treatability Study Quality Assurance Project Plan (QAPP) (dated September 8, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Butte Priority Soils Operable Unit Draft Final Leak Detection Monitoring Plan (dated May 13, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Diggings East 100% Remedial Design Package Submittal (dated May 29, 2006), Emma Rott
PDF
Re: Conditional Approval Letter for Diggings East 95 % Remedial Design Package Submittal (dated March 25, 2006), the Silver Bow Creek Conservation Area (SBCCA) – 95 Percent Programmatic Technical Specifications Submittal (dated March 25, 2026), the Butte Priority Soils Operable Unit (BPSOU) SBCCA Operations and Maintenance (O&M) Plan (dated March 24, 2026), and the SBCCA Final Principles for a Greener Cleanup Report (dated February 4, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Draft Final 2026 Interim Site-Wide Groundwater Monitoring Quality Assurance Project Plan (dated May 6, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Draft Final Silver Bow Creek Conservation Area Materials Management Plan Revision 1 (dated March 24, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Final Silver Bow Creek Conservation Area (SBCCA) Construction Quality Assurance Plan and Draft Final Silver Bow Creek Conservation Area (SBCCA) Construction Monitoring Quality Assurance Project Plan (dated April 7, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for Revised Clark Tailings Consolidated Waste Management Area (CTCWMA) Site Investigation Data Summary Report 2024 and Response to EPA Comment Letter (dated February 24, 2026), Emma Rott
PDF
Re: Conditional Approval letter for the Butte Priority Soils Operable Unit (BPSOU) Butte Treatment Lagoons (BTL) Groundwater Treatment System Quarterly Operation and Maintenance Report – Quarter 3 2025 (dated December 23, 2025), Emma Rott
PDF
Re: Conditional approval Letter for the Butte Priority Soils Operable Unit (BPSOU) Clark Tailings Consolidated Waste Management Area (CTCWMA) Site Investigation Quality Assurance Project Plan (QAPP) (dated April 16, 2026), Emma Rott
PDF
Re: Conditional approval Letter for the Butte Priority Soils Operable Unit (BPSOU) Clark Tailings Consolidated Waste Management Area (CTCWMA) Site Investigation Quality Assurance Project Plan (QAPP) (dated June 1, 2026), Emma Rott
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit (BPSOU) Silver Bow Creek Conservation Area (SBCCA) Operations and Maintenance (O&M) Plan (dated May 29, 2006), Emma Rott
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit Unreclaimed Sites Quality Assurance Project Plan, Emma Rott
PDF
Re: Conditional approval letter for the Butte Priority Soils Operable Unit Unreclaimed Sites Quality Assurance Project Plan, Emma Rott
PDF
Re: Conditional approval letter for the Draft Final Butte Mine Waste Repository Operations and Maintenance (O&M) Plan (dated August 3, 2026), Emma Rott
PDF
Re: Conditional Approval Letter for the Draft Final Butte Reduction Works (BRW) Smelter Area Mine Waste Remediation and Contaminated Groundwater Hydraulic Control Site Pre-Design Investigation (PDI) Evaluation Report (dated September 12, 2025), Emma Rott
PDF
Re: Conditional approval Letter for the Final Revised Silver Bow Creek Conservation Area (SBCCA) Construction Quality Assurance Plan (CQAP) (dated May 28, 2026) and the Final Silver Bow Creek Conservation Area (SBCCA) Construction Monitoring Quality Assurance Project Plan (QAPP) (dated May 28, 2026), Emma Rott
PDF
Re: Conditional approval letter for the Final Silver Bow Creek Conservation Area Materials Management Plan (dated May 28, 2026), Emma Rott
PDF
Re: Conditional Approval Letter with comments for Butte Priority Soils Operable Unit (BPSOU) Draft Final 2026 Interim Site-Wide Surface Water Monitoring Quality Assurance Project Plan (QAPP) (dated February 4, 2026), Emma Rott
PDF
Draft Butte Priority Soils Operable Unit (BPSOU) Silver Bow Creek Conservation Area (SBCCA) Operations and Maintenance (O&M) Plan, Stantec Consulting Services, Inc.
PDF
RE: Response to Comment Letter (dated June 11, 2026) for the Butte Priority Soils Operable Unit (BPSOU) Draft 2025 Butte Reclamation Evaluation System (BRES) Corrective Action Plans for Reclaimed Sites (dated January 30, 2026), Brandon Warner
PDF
BPSOU Grove Gulch Sedimentation Bay Draft Remedial Action Construction Completion Report (CCR), Woodard & Curran
PDF
Clark Tailings Consolidated Waste Management Area (CTCWMA) Site Investigation Draft Data Summary Report 2024 Surface Water, Groundwater, and Soil Characterization, Woodard & Curran
PDF
Clark Tailings Consolidated Waste Management Area Site Investigation Quality Assurance Project Plan (QAPP), Woodard & Curran