Prepared By:
Montana Resources; Atlantic Richfield Company
Document Type
Government Report
Publication Date
Fall 11-26-2024
Subject Area
Butte
Recommended Citation
Thompson, Mark and Griffis, Dave, "Re: Butte Mine Flooding Operable Unit Berkeley Pit and Discharge Pilot Project – October 2024 Monthly Discharge Monitoring Report" (2024). Silver Bow Creek/Butte Area Superfund Site. 1254.
https://digitalcommons.mtech.edu/superfund_silverbowbutte/1254
Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.
Included in
Environmental Health and Protection Commons, Environmental Indicators and Impact Assessment Commons, Environmental Monitoring Commons
Comments
Operations Summary:
The Berkeley Pit and Discharge Pilot Project (Pilot Project) Discharge System Polishing Facility did not discharge off-site from October 1 through October 31, 2024, and was only operated for maintenance activities during this reporting period. The Polishing Facility continued to operate with all flows directed off-spec to Montana Resources’ dredge pond during the reporting period. Reverse Osmosis (RO) Reject includes flows that were produced during routine permeate flushes; this RO Reject was discharged directly to the Berkeley Pit.